Webuild Logo

SECI Vs. WFRPL: Judicial Clarification on Renewable Energy Project Timelines

BACKGROUND This case involves a dispute between Solar Energy Corporation of India Limited (SECI) and Wind Four Renergy Private Limited (WFRPL) over delays in commissioning a wind power project. WFRPL entered into Power Purchase Agreements to supply wind energy, but delays in t

BACKGROUND


This case involves a dispute between Solar Energy Corporation of India Limited (SECI) and Wind Four Renergy Private Limited (WFRPL) over delays in commissioning a wind power project. WFRPL entered into Power Purchase Agreements to supply wind energy, but delays in the Long-Term Access (LTA) for transmission caused significant setbacks. Although, MNRE granted a 60-day extension, WFRPL sought extension, leading to an appeal to the CERC and subsequently to Appellate Tribunal for Electricity (APTEL). The Honorable Supreme Court ultimately overruled APTEL’s decision, emphasizing necessity of adhering to project timelines.


Cumulative SRT Capacity Installed – State Wise Track till Nov’2023


The case "Solar Energy Corporation of India Limited (SECI) vs. Wind Four Renergy Private Limited (WFRPL)" revolved around delays in the commissioning of a wind power project.

WFRPL had entered into five Power Purchase Agreements (PPAs) with Power Trading Company India Limited to supply wind power, with SECI acting as the implementing agency.

The project faced delays due to the inter-state transmission system's Long-Term Access (LTA) not being operationalized on time by Power Grid Corporation of India, which was only completed on 14th April, 2019.

Due to these delays, the Ministry of New and Renewable Energy granted an extension for the project's commissioning by 60 days after the LTA became operational.

SECI accepted that WFRPL's commissioning date would be extended to 13th June, 2019.

However, WFRPL claimed they were not informed of the LTA operationalization until 22nd November, 2019 and sought further extensions.

The Central Electricity Regulatory Commission (CERC) granted an additional 132-day extension, which SECI accepted, but WFRPL appealed to the Appellate Tribunal for Electricity (APTEL), which decided that the 132-day extension should start from 11th January, 2022.

SECI Challenged this decision in the Supreme Court, which found APTEL’s decision irrational and contrary to the scheme and PPA.


×

Ready to learn more about Eninrac? REQUEST DEMO

Get started with
EI Market personalised demo

Complete the form to connect with our sales team and see the Visionboard platform in action. Discover how Eninrac helps your teams eliminate poor market research experiences and drive actionable insights.

Powered by Why
Start up india Logo
MSME Logo
REQUEST DEMO

By providing this information, you grant consent that we may process your personal data in accordance with our Privacy Statement.

By submitting this form, you grant consent to receive marketing information from eninrac as set out in our Terms of Service & Privacy Statement. You may unsubscribe at any time. Privacy Policy.